PROJECT ALLOCATION
Agra Smart City Limited has conducted as-is scenario assessments, prepared detailed project reports, feasibility reports, and released tenders for the various projects outlined below. 
 
Early wins have been achieved in improving the access roads and facilities to the East, West, and South gates of Taj Mahal. E-bike sharing system has been launched on a pilot basis. Street lights have been changed from sodium vapor to LED to reduce energy consumption.
 
PROJECT ALLOCATION SUMMARY
S.No. Particular SCM Projects (Cost In INR Cr)
  No. Of Projects Cost
  Total Number Of Projects 23 1364.06
1 DPR Prepared 23 1364.06
2 NIT Issued 18 468.08
3 Tender Approved 10 419.51
4 Work Started (On Going) 6 411.93
5 Work Completed 0 0

 

SCM PROJECTS (23)
S.NO Projec's Name Cost (Rs. in Cr.)
A ABD Area Projects  
1 Development Of Street Vending Zone 3.45
2 E-Toilet 4.07
3 Improvement of vicinity of Lesser Known Heritage Monuments (Development of Heritage walk) 3.56
4 Junctions Improvement Ph-1 (Civil) Ph-2 (Signage)  7.68
5 Beautification and Streetscaping of Fathebad Road  105.93
6
Intensive Beautification of Heritage walk within 2Km Radius around Tajmahal (civil & illumination works)
9.70
7 Façade improvement of Traditional Houses 0.99
8 Rehabilitation of Major Roads 85.43
9 Rehabilitation of Minor Roads 171.77
10 Solar Installation 26.53
11 Micro Skill Development Centre 2.02
12 Provision of Municipal Health Centre/kiosk,Women Distress centre, Anganwadi 5.29
13 Upgradation of Municipal Schools 1.30
14 Provision of Quick Response Centre,Smart Police Kiosks, Digital Literacy Centre 8.68
15 Waste Management 3.83
16 Pilot 24x7 water supply(Metering,SCADA system), Fire Hydrant 134.07
17 Taj East Drain Improvement Plan 26.10
18 Sewerage network 145.42
B Pan city Projects  
19 MSI-ICCC(Integrated command and control center) 245.44
20 Bus Shelters 20.00
21 Junction Improvement-II: 26.95
22 Multilevel car Parking 144.97
23 Purchase of Electrical Buses 213.58
 
 
DPR SUBMITTED (23)
S.No Name Of Projects Cost (Rs) Cr.
A ABD (Area Based Project)  
1 Development of Street Vending Zones 3.45
2 E-Toilet 4.07
3 Development of Heritage walk 3.56
4 Junctions Improvement Ph-1(Civil) Ph-2(Signage) 7.68
5 Beautification and Streetscaping of Fatehabad Road 105.93
6 Intensive Beautification of Heritage walk within2Km Radius around Tajmahal 9.70
7 Micro skill Development center and women SHG center 2.02
8 Solar Installation Project 26.53
9 Solid Waste Management 3.83
10 Smart Healthcare kiosk on rental basis at 10 locations in Agra and Municipal Health center and women distress center 5.29
11 Taj East Drain Improvement Plan 26.10
12 Façade improvement of Traditional Houses 0.99
13 Upgradation of school Civil works 1.30
14 Digital Education in schools/Digital Literacy Center 0.61
15 Providing 24x7 water supply with (Metering,SCADA system), Fire Hydrant 134.07
16 Sewerage Network 145.42
17 Rehabilitation of Major Roads 85.43
18 Rehabilitation of Minor Roads 171.77
B Pan city  
19 MSI-ICCC(Integrated command and control center) 245.44
20 Bus shelter on PPP mode 20.00
21 Electrical Buses:FAME Scheme :Proposal Submitted 213.58
22 Junction Improvement-II: (DPR Submitted Phase-1:7junctions (Rs.2.30 cr), discussions are in progress for overlapping junctions to be done by private parties) Total Cost:26.95 2.30
23 Multilevel Car Parking 144.97

 Total Project cost of DPR Submitted:1364.04cr 

 
NIT ISSUED (18)
S.No. Name Of Projects Cost (Rs) Cr.
A ABD Projects  
1 Development of Street Vending Zones 3.45
2 Development of Heritage walk in Agra 3.56
3

a) Junction Improvement-Civil Works

b) Junction Improvement-Signage

6.86
0.81
4 Beautification and Streetscaping of Fathebad Road. 105.93
5

a) Intensive Beautification of heritage walk within 2Km Radius around Tajmahal-Civil Works

b) Intensive Beautification of heritage walk within 2Km Radius around TajmahalIllumination works

3.13
6.56
6 Development of Public E-Toilet/IP toilet/Self cleaning toilet under EPC mode project-8 locations 4.07
7 Micro skill Development center and Women SHG center 2.02
8 Façade improvement of Traditional Houses 0.99
9 Solar Installation Project 26.54
10 Upgradation of Municipal School –Civil works 1.30
11 Digital Education in schools/Digital Literacy Center 0.61
12 Taj East Drain Improvement Plan 26.10
13 Municipal Health center and women distress center with staff NGO 4.28
14 Smart Healthcare kiosk on rental basis at 10 locations in Agra 1.01
15 Municipal Solid Waste Management 3.14
B Pan city  
16 Master System Integrator work for Integrated Control System (ICCC) 245.44
17 Bus shelter on PPP mode 20.00
18 Junction Improvement Pan city 2.30

 Total Project cost of NIT Issued:468.08cr 

 

PROJECT WORK ON GOING (6)
Sr. No Project Name Actual Cost as per work order (Cr.) Work Done Issued Date Contractors Name
1 Development of Heritage walk in Agra 3.46 5/6/18 Vinod Enterprise
2 Junction Improvement (Civil work ; Signages) 6.97 Civil works:19/6/18 Signages works :27/6/18 Civil works: M.G Constructions Signages works: Sushil Singal
3 Development of Street Vending Zones (3 locations) 3.33 22/6/18, Sushil Singal
4 Intensive Beautification of heritage walk within 2Km Radius around Tajmahal-Civil Works ;illumination works 9.64 Civil works:23/ 8/18 Illuminatio n works: Garg Re-Surfacing & Construction
5 Beautification and Streetscaping of Fatehabad Road. 105.88 23/8/18 Radhika - RPG – AARPEE Infra (JV)
6 MSI-ICCC 282.65 29/8/18 Bharat Electronics Ltd in JV with IL&FS, Synergy ltd.